In scheduling problem for automatic assembly, planning of task sequence is closely related with resource allocation. However, they have been separately carried out with little interaction in previous work. In assembly planning problem, there are many feasible sequences for one mechanical product. In order to find the best assembly sequence, we have to decide the cost function for each task a priori and make decision based on summation of costs in sequence. But the cost of each task depends on the machine which executes the allocated task and it becomes difficult to estimate an exact cost of each task at planning stage. Moreover, no concurrent operation is taken into account at planning stage. Therefore, we must consider the sequence planning and the machine allocation simultaneously. In this paper, we propose a new scheduling method in which sequence planning and machine allocation are considered simultaneously. First of all, we propose a modeling method for an assembly sequence including a manufacturing environment. Secondly, we show a guideline in order to determine the estimate function in A* algorithm for assembly scheduling. Thirdly, a new search method based on combination of A* algorithm and supervisor is proposed. Fourthly, we propose a new technique which can take into consider the repetitive process in manufacturing system so as to improve the calculation time. Finally, numerical experiments of proposed scheduling algorithm are shown and effectiveness of proposed algorithm is verified.
The copyright of the original papers published on this site belongs to IEICE. Unauthorized use of the original or translated papers is prohibited. See IEICE Provisions on Copyright for details.
Copy
Akio INABA, Fumiharu FUJIWARA, Tatsuya SUZUKI, Shigeru OKUMA, "Timed Petri Net Based Scheduling for Mechanical Assembly Integration of Planning and Scheduling" in IEICE TRANSACTIONS on Fundamentals,
vol. E81-A, no. 4, pp. 615-625, April 1998, doi: .
Abstract: In scheduling problem for automatic assembly, planning of task sequence is closely related with resource allocation. However, they have been separately carried out with little interaction in previous work. In assembly planning problem, there are many feasible sequences for one mechanical product. In order to find the best assembly sequence, we have to decide the cost function for each task a priori and make decision based on summation of costs in sequence. But the cost of each task depends on the machine which executes the allocated task and it becomes difficult to estimate an exact cost of each task at planning stage. Moreover, no concurrent operation is taken into account at planning stage. Therefore, we must consider the sequence planning and the machine allocation simultaneously. In this paper, we propose a new scheduling method in which sequence planning and machine allocation are considered simultaneously. First of all, we propose a modeling method for an assembly sequence including a manufacturing environment. Secondly, we show a guideline in order to determine the estimate function in A* algorithm for assembly scheduling. Thirdly, a new search method based on combination of A* algorithm and supervisor is proposed. Fourthly, we propose a new technique which can take into consider the repetitive process in manufacturing system so as to improve the calculation time. Finally, numerical experiments of proposed scheduling algorithm are shown and effectiveness of proposed algorithm is verified.
URL: https://global.ieice.org/en_transactions/fundamentals/10.1587/e81-a_4_615/_p
Copy
@ARTICLE{e81-a_4_615,
author={Akio INABA, Fumiharu FUJIWARA, Tatsuya SUZUKI, Shigeru OKUMA, },
journal={IEICE TRANSACTIONS on Fundamentals},
title={Timed Petri Net Based Scheduling for Mechanical Assembly Integration of Planning and Scheduling},
year={1998},
volume={E81-A},
number={4},
pages={615-625},
abstract={In scheduling problem for automatic assembly, planning of task sequence is closely related with resource allocation. However, they have been separately carried out with little interaction in previous work. In assembly planning problem, there are many feasible sequences for one mechanical product. In order to find the best assembly sequence, we have to decide the cost function for each task a priori and make decision based on summation of costs in sequence. But the cost of each task depends on the machine which executes the allocated task and it becomes difficult to estimate an exact cost of each task at planning stage. Moreover, no concurrent operation is taken into account at planning stage. Therefore, we must consider the sequence planning and the machine allocation simultaneously. In this paper, we propose a new scheduling method in which sequence planning and machine allocation are considered simultaneously. First of all, we propose a modeling method for an assembly sequence including a manufacturing environment. Secondly, we show a guideline in order to determine the estimate function in A* algorithm for assembly scheduling. Thirdly, a new search method based on combination of A* algorithm and supervisor is proposed. Fourthly, we propose a new technique which can take into consider the repetitive process in manufacturing system so as to improve the calculation time. Finally, numerical experiments of proposed scheduling algorithm are shown and effectiveness of proposed algorithm is verified.},
keywords={},
doi={},
ISSN={},
month={April},}
Copy
TY - JOUR
TI - Timed Petri Net Based Scheduling for Mechanical Assembly Integration of Planning and Scheduling
T2 - IEICE TRANSACTIONS on Fundamentals
SP - 615
EP - 625
AU - Akio INABA
AU - Fumiharu FUJIWARA
AU - Tatsuya SUZUKI
AU - Shigeru OKUMA
PY - 1998
DO -
JO - IEICE TRANSACTIONS on Fundamentals
SN -
VL - E81-A
IS - 4
JA - IEICE TRANSACTIONS on Fundamentals
Y1 - April 1998
AB - In scheduling problem for automatic assembly, planning of task sequence is closely related with resource allocation. However, they have been separately carried out with little interaction in previous work. In assembly planning problem, there are many feasible sequences for one mechanical product. In order to find the best assembly sequence, we have to decide the cost function for each task a priori and make decision based on summation of costs in sequence. But the cost of each task depends on the machine which executes the allocated task and it becomes difficult to estimate an exact cost of each task at planning stage. Moreover, no concurrent operation is taken into account at planning stage. Therefore, we must consider the sequence planning and the machine allocation simultaneously. In this paper, we propose a new scheduling method in which sequence planning and machine allocation are considered simultaneously. First of all, we propose a modeling method for an assembly sequence including a manufacturing environment. Secondly, we show a guideline in order to determine the estimate function in A* algorithm for assembly scheduling. Thirdly, a new search method based on combination of A* algorithm and supervisor is proposed. Fourthly, we propose a new technique which can take into consider the repetitive process in manufacturing system so as to improve the calculation time. Finally, numerical experiments of proposed scheduling algorithm are shown and effectiveness of proposed algorithm is verified.
ER -